progress of the construction

04-15 : expension of the site. 

05-15 : the plot was cleaned from eucalypts, excavation of the garage, surveying foundation.

06-15: ironwork of the garagefloor, concrete, pillars to the first floor

07-15: foundation first floor, stairs in concrete.

08-15: concrete first floor, pillars to the ceiling.

09-15: construction of the ceiling

10-15: construction of the roof

11-15: tiles on the roof

02-16: sewer pipes

03-16: waterworks

04-16: electric lines, tv and internet

05-16: stucco basement

06-16: bituminous coverage of the flat roof

06-16: construction of the sliding doors to the bedrooms

06-16: construction of the swimmingpool 10 x 4 m

07-16: construction of the exterior stairs

07-16: interior stucworks

08-16: finishing exterior

09-16: all connections

10-16: streetworks

11-16: equipment for bathrooms, bedrooms, heating

12-16: delivery of the project