progress of the construction
04-15 : expension of the site.
05-15 : the plot was cleaned from eucalypts, excavation of the garage, surveying foundation.
06-15: ironwork of the garagefloor, concrete, pillars to the first floor
07-15: foundation first floor, stairs in concrete.
08-15: concrete first floor, pillars to the ceiling.
09-15: construction of the ceiling
10-15: construction of the roof
11-15: tiles on the roof
02-16: sewer pipes
03-16: waterworks
04-16: electric lines, tv and internet
05-16: stucco basement
06-16: bituminous coverage of the flat roof
06-16: construction of the sliding doors to the bedrooms
06-16: construction of the swimmingpool 10 x 4 m
07-16: construction of the exterior stairs
07-16: interior stucworks
08-16: finishing exterior
09-16: all connections
10-16: streetworks
11-16: equipment for bathrooms, bedrooms, heating
12-16: delivery of the project